The Address Residences Jumeirah Resort + Spa, an iconic development by Emaar Hospitality Group located in a prime location in JBR, has reached another breakthrough with Multiplex Construction LLC being recently appointed as main contractor for the project.

The construction is now in full swing and following are the milestones of progress:

    • Contractor fully mobilised with commencement of works to the basement areas
    • Three tower cranes are now erected with the erection of the fourth crane in January 2018
    • Construction of the basement slabs to commence January 2018
    • West Tower:
      • Basement area Waterproofing completed
      • Lift pit bases and walls casting (1,500m3 concrete) on target for completion week ending 14th December 2017
      • Casting of the raft slab (8,000m3 of concrete) planned completion December 2017
    • East Tower:
      • Basement area Waterproofing in final stages of completion
      • Lift pit bases and walls casting (2,000m3 concrete) on target for completion December 2017 end
      • Casting of the raft slab (8,000m3 concrete) planned January 2018

The project offers a unique opportunity to buy freehold serviced and residential apartments in one of Dubai’s most prestigious locations. It is the last available plot to ever be built on Jumeirah Beach Walk in Dubai Marina making it a strategic investment option.Since the official launch in October 2016, The Address Residences Jumeirah Resort + Spa has been named ‘an architectural marvel’ by the media, and it is one of the most sought after projects in Dubai and internationally.

To find out more about premium and luxury property investment opportunities by The Address, please visit our dedicated sales center: 2nd Floor, The Address Dubai Marina or pass by our promotional kiosk at The Beach Mall, JBR.

Or simply give us a call at 800 Hamptons / enquiries@hamptons.ae
Stay tuned for ongoing project construction updates.

Get In Touch